Construction time
20 – 45 working days, dependent on house size
Foundation type
Screw piles, slab or concrete post foundation
Roof pitch
Model and client choice dependent, from 25° to 35°
Personalisation
All house models can have slight changes to satisfy client’s exact needs.
Core materials
- CLT (cross-laminated timber)
- Glulam (glue-laminated timber)
Beams and posts of the house are engineered from glulam, whereas the floor, ceiling, interior walls and any intermediate floors are from CLT.
Benefits
- Precision engineering and CNC cutting delivers microlevel accuracy
- ±0.1-0.5 mm tolerances delivered by machine cutting greatly improve the overall energy efficiency and airtightness of the building envelope
- Quick installation
- Natural "feel" for wood a primary aesthetic feature
House Design Principles
- Space and light
- Premium quality materials and finishes
- Precision engineering and CNC cutting for a long building life span
- Quick installation
- Personalisation options (house length, width, height, interior walls and room locations as long as core structures stay the same)
Building options
We offer full “keys to the house” solution, but can also install the house until structural works are delivered and the house would be 100% finished externally.
- Exterior ready (stone or steel roof)
- "Keys to the house"
- "Keys to the house" with foundation
External works up to a built foundation (before house installation) are usually organised by the client with support and foundation plans supplied by us. If required, we can pre-fabricate concrete posts for foundation and install the house from foundation.
Heating options
We offer a variety of solutions for house heating and cooling, dependent on the house location and client preferences.
- Air-to-air heat pump for heating and cooling 60 m² houses
- Air-to-air heat pump for partial floor heating (shown on the photo) + cooling 60 m² houses
- Air-to-water heat pump for floor heating + cooling available for all models
Special details and add-ons
Standard ODYL characteristics for all models by design
- Hidden rain-gutters
- Flush threshold sliding doors (sliding doors' locations chosen by the client)
- Solid wooden doors
Optional standard add-ons
- LED lights for all rooms
- Terrace on glulam beams (size dependent on the model)
- Personalised add-ons are possible, pricing TBC
Personalisation
60 m² and 85 m² house models can have slight changes structurally, such as interior walls’ location changes + any interior design changes, such as the choice of parquet or bathroom fittings without any extra charge, besides material cost.
100+ m² houses, 3+ bedroom houses or any other tailor made projects are tailored to the clients’ needs, unless the client would like to use an existing project.
Tailor made floor plans, architectural models as well as 3D renders are done in cooperation with the client. Any tailor made plan costs €1000 EUR + VAT to fix the initial cost for the project for the client to decide whether they would like to progress.
Personalisation
60 m² and 85 m² house models can have slight changes structurally, such as interior walls’ location changes + any interior design changes, such as the choice of parquet or bathroom fittings without any extra charge, besides material cost.
100+ m² houses, 3+ bedroom houses or any other tailor made projects are tailored to the clients’ needs, unless the client would like to use an existing project.
Tailor made floor plans, architectural models as well as 3D renders are done in cooperation with the client. Any tailor made plan costs €1000 EUR + VAT to fix the initial cost for the project for the client to decide whether they would like to progress.
Installation time
“Structural” – house ready externally, only interior works to be done
- 60 m² house = 7-10 working days from foundation
- 85 m² house = 10-12 working days
- 100+ m² house = 14-16 working days
“Keys to the house”
- 60 m² house = 20-25 working days
- 85 m² house = 25-30 working days
- 100+ m² house = 40-45 working days
Notes
- Exact installation time is dependent on plor location and chosen add-ons
- 2+ houses installed at the some time decrease the installation time per house